NORTHBANK CIVIL AND MARINE, LLC Federal Contracts — Government Award History
Total (All Time)$115M
Latest FY$18M
Primary AgencyDepartment of Defense
NORTHBANK CIVIL AND MARINE, LLC has received $115M in total federal contract awards
across 6 fiscal year(s). ▼ 48.6% vs FY2024 Peak year was FY2024 ($36M).
Primary awarding agency: Department of Defense.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2025 | $18.4M | 4건 | Department of Defense | |
| FY2024 | $35.8M | 6건 | Department of Defense | |
| FY2023 | $25.2M | 6건 | Department of Defense | |
| FY2021 | $11.7M | 6건 | Department of Defense | |
| FY2020 | $13.5M | 7건 | Department of Defense | |
| FY2019 | $10.2M | 3건 | Department of Defense |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2025-11-21 | Department of Defense | $19.9M | ICE HARBOR INTAKE GATE HYDRAULIC SYSTEM UPGRADE |
| 2017-08-30 | Department of the Interior | $15.8M | IGF::OT::IGF CLE ELUM DAM FISH PASSAGE FACILITY, JUVENILE FACILITY-TUNNEL, YAKIM |
| 2018-09-04 | Department of Defense | $14.1M | IGF::OT::IGF DETROIT DAM TAINTER GATE REHABILITATION |
| 2024-08-12 | Department of Defense | $13.3M | BONNEVILLE DAM – SPILLWAY GATE REPAIR PIT UPGRADES |
| 2023-01-24 | Department of Defense | $11.0M | MCNARY LOCK AND DAM DRAINAGE, UNWATERING AND EQUALIZATION (DUE) SYSTEM REHABILIT |
| 2025-09-01 | Department of Defense | $8.6M | MNA – LEVEE PUMP STATION UPGRADES TO#3. |
| 2024-03-08 | Department of Defense | $7.0M | MNA LEVEE PUMP STATION UPGRADE TASK ORDER 0001 |
| 2024-08-21 | Department of Defense | $6.5M | MNA – LEVEE PUMP STATION UPGRADES TO#2 |
| 2023-05-10 | Department of Defense | $6.2M | CJD SPILLWAY SUMP PUMPS AND CONTROLS UPGRADE |
| 2025-11-01 | Department of Defense | $5.9M | CHIEF JOSEPH DAM UPSTREAM MONOLITH JOINT SEAL, BRIDGEPORT, WA SEE ATTACHED SPEC |
| 2019-06-26 | Department of Defense | $5.8M | HAHD SPILLWAY GATES REHAB |
| 2025-05-01 | Department of Defense | $5.4M | DWA CONSTRUCTION FOR THE DNFH ELECTRICAL DISTRIBUTION BUILDING |
| 2020-09-30 | Department of Defense | $5.4M | DWA RO VALVE UPGRAGE |
| 2024-09-23 | Department of Defense | $4.7M | BONNEVILLE CONCRETE FISH LADDER REBUILD PROJECT TO EASE PASSAGE OF LAMPREY AND S |
| 2023-03-07 | Department of Defense | $4.3M | WILLAMETTE FALLS LOCKS SEISMIC UPGRADES |
| 2021-02-18 | Department of Defense | $4.1M | DEXTER DAM – MANUFACTURE NEW 25 TON INTAKE GANTRY CRANE |
| 2025-09-12 | Department of Defense | $4.1M | MCNARY LOCK ELEVATOR NO. 2 REPLACEMENT |
| 2020-09-30 | Department of Defense | $3.3M | THE DALLES GATE REPAIR PIT AND STORAGE UPGRADES |
| 2018-01-12 | Department of Defense | $3.2M | IGF::OT::IGF MCNARY PRECIPITRON REPLACEMENT DESIGN BUILD |
| 2016-04-22 | Department of Defense | $2.9M | IGF::OT::IGF COUGAR DAM OIL SPILL PREVENTION SYSTEM |