Total (All Time)$17M
Latest FY$418,645
Primary AgencyGeneral Services Administration
ABM FACILITY SUPPORT SERVICES, LLC has received $17M in total federal contract awards
across 4 fiscal year(s). ▲ 7.7% vs FY2022 Peak year was FY2021 ($16M).
Primary awarding agency: General Services Administration.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2023 | $418,645 | 10건 | General Services Administration | |
| FY2022 | $388,612 | 11건 | General Services Administration | |
| FY2021 | $15.6M | 9건 | General Services Administration | |
| FY2020 | $421,309 | 3건 | General Services Administration |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2020-10-01 | General Services Administration | $15.1M | INSTALLATION AND LONG TERM MEASUREMENT&VERIFICATION OF ENERGY CONSERVATION MEASU |
| 2019-09-25 | General Services Administration | $1.1M | ENERGY SAVINGS PERFORMANCE CONTRACT INVOLVES THE INSTALLATION AND LONG-TERM MEAS |
| 2019-01-01 | General Services Administration | $682,175 | IGF::OT::IGF DATA CENTER INFRASTRUCTURE MANAGEMENT SYSTEM UPGRADES NATIONAL OC |
| 2024-09-26 | Department of Energy | $436,881 | THE WESTERN AREA POWER ADMINISTRATION (WAPA), SIERRA NEVADA REGION (SNR), REQUIR |
| 2020-05-11 | General Services Administration | $246,059 | CONTRACTOR TO INSTALL NEW PUMPS AT 1000 GALLIHER DRIVE, FAIRMONT, WEST VIRGINIA |
| 2025-04-16 | Department of Energy | $173,053 | SNR FOLSOM HQ COMM ROOM HVAC REPLACEMENT OF UNIT ACU-4. INCLUDES EQUIPMENT AND I |
| 2021-06-16 | General Services Administration | $154,775 | BATTERY REPLACEMENT PROJECT AT THE ISR BUILDING, 1000 GALLIHER DRIVE, FAIRMONT, |
| 2022-12-07 | General Services Administration | $150,334 | NOAA GOES UPS CAPACITORS AND FANS PROJECT, NOAA 1000 GALLIHER DRIVE FAIRMONT WV, |
| 2021-04-26 | General Services Administration | $135,655 | BATTERY REPLACEMENT AT NOAA, 1000 GALLIHER DRIVE, FAIRMONT, WEST VIRGINIA |
| 2023-04-12 | General Services Administration | $107,379 | FY23 SWITCHGEAR PREVENTATIVE MAINTENANCE FOR NOAA LOCATED IN FAIRMONT, WEST VIRG |
| 2020-08-12 | General Services Administration | $91,939 | CONTRACT NO.: GS-03P-13-DX-D-0021 TASK/AWARD NO.: 47PD1020F0152 PDN: EP-47PD1020 |
| 2021-11-01 | General Services Administration | $88,050 | REPLACE THE THE INSULATION ON THE GOES CHILLED WATER PIPING IN ROOM 378 AT THE I |
| 2020-08-13 | General Services Administration | $83,311 | ISR BUILDING, 1000 GALLIHER DR, FAIRMONT, WV, 26554-8826 INSTALL TWO STARLINE BU |
| 2022-05-01 | General Services Administration | $67,274 | DAP NEW CONTROLLERS REPLACEMENT 13 CRAC UNITS |
| 2025-09-05 | Department of Energy | $65,203 | WAPA SNR REQUIREMENT FOR THREE (3) HVAC UNITS AT THE FOLSOM SUBSTATION (FOL), SA |
| 2022-09-06 | General Services Administration | $58,490 | NOAA NESCC 359 PDU CARDS PROJECT, NOAA, 1000 GALLIHER DRIVE FAIRMONT WV, 26554-8 |
| 2021-08-25 | General Services Administration | $56,888 | TITLE: NESCC SCADA LICENSES LOCATION: 1000 GALLIHER DRIVE FAIRMONT WV 26554-8 |
| 2020-11-18 | General Services Administration | $49,430 | UPGRADE THE AMP POLE BREAKERS AS A TASK ORDER AGAINST CONTRACT # GS-03-P-16-DX-D |
| 2025-12-10 | Department of Defense | $44,052 | PURCHASE REPLACEMENT CUSTOMIZED COMPRESSOR AND PARTS |
| 2023-04-12 | General Services Administration | $41,704 | NOAA GOES FY23 SWITCHGEAR PM PROJECT, NOAA, 1000 GALLIHER DRIVE FAIRMONT WV, 265 |