D&S INTERNATIONAL, LLC Federal Contracts — Government Award History
Total (All Time)$3M
Latest FY$2M
Primary AgencyDepartment of Defense
D&S INTERNATIONAL, LLC has received $3M in total federal contract awards
across 2 fiscal year(s). ▲ 156.2% vs FY2020 Peak year was FY2021 ($2M).
Primary awarding agency: Department of Defense.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2021 | $2.1M | 8건 | Department of Defense | |
| FY2020 | $803,793 | 3건 | Department of Defense |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2022-08-30 | Department of Defense | $1.7M | B.45 COMMOM AREA REPAIRS-BASIC |
| 2021-09-20 | Department of Defense | $1.1M | BLDG #77 UPSTAIRS & DOWNSTAIRS LATRINES |
| 2022-12-20 | Department of Transportation | $432,338 | REMOVAL AND REPLACEMENT OF GROUND LEVEL RAISED FLOOR SYSTEMS AT THE DFWA AND DFW |
| 2020-09-02 | Department of Defense | $369,328 | CONSTRUCT USDB GREENHOUSE AT BLDG.#1169 – THE WORK CONSISTS OF FURNISHING ALL PL |
| 2020-06-09 | Department of Defense | $249,601 | RENOVATE SERVER ROOM B.45REPAIR RENOVATE 1W SERVER ROOM AT BLDG.#45 – THE WORK C |
| 2021-07-01 | Department of Defense | $212,948 | REPAIR CHILLER AT SSQ, BLDG. 635 |
| 2021-05-25 | Department of Defense | $209,375 | REPAIR LATRINE, FLOORS AND FIRE ALARM SYSTEM AT BLDG.#364 – THE WORK CONSISTS O |
| 2020-06-24 | Department of Defense | $184,864 | REPLACE EXTERIOR DOORS AT BLDG.#52 NORTH-SIDE – THE WORK CONSISTS OF FURNISHING |
| 2021-07-21 | Department of Defense | $164,928 | LIGHTING CONTROL UPGRADE – B.127 |
| 2021-08-18 | Department of Defense | $126,531 | CONSTRUCT OSA ROOM AT SHERMAN HALL – B.52 |
| 2021-08-25 | Department of Defense | $77,052 | REPAIR FIRE ALARM – B.842 |
| 2023-09-27 | Department of Defense | $72,480 | REPAIR DEGRADED RAISED ACCESS FLOORING IN BUILDING 153 SERVER ROOMS. |
| 2021-06-03 | Department of Agriculture | $64,729 | INSTALLING NEW HEAT EXCHANGER FOR THE PURPOSE OF ISOLATION THE EXTERIOR PORTION |
| 2021-05-27 | Department of Defense | $60,822 | REPAIR LEAKING FOUNDATION AT BLDG.#314 – THE WORK CONSISTS OF FURNISHING ALL PL |