Total (All Time)$3M
Latest FY$327,804
Primary AgencyDepartment of the Interior
HEDEFINE ENGINEERING & DESIGN INC has received $3M in total federal contract awards
across 6 fiscal year(s). ▼ 41.4% vs FY2024 Peak year was FY2023 ($886,000).
Primary awarding agency: Department of the Interior.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2025 | $327,804 | 3건 | Department of the Interior | |
| FY2024 | $559,853 | 6건 | Department of the Interior | |
| FY2023 | $886,000 | 6건 | Department of the Interior | |
| FY2022 | $459,275 | 11건 | Department of the Interior | |
| FY2021 | $522,526 | 15건 | Department of the Interior | |
| FY2020 | $365,498 | 8건 | Department of the Interior |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2023-08-30 | Department of the Interior | $646,625 | ACAD 309000 EMPLOYEE HOUSING HARDEN FARM PDSD & DDCD |
| 2024-09-10 | Department of the Interior | $381,716 | ACAD 30090 – HARDEN FARMS EMPLOYEE HOUSING PHASE 1C |
| 2020-03-31 | Department of the Interior | $214,620 | TITLE I AND TITLE II ARCHITECT AND ENGINEERING SERVICES TO REPLACE THE JORDAN PO |
| 2026-01-21 | Department of the Interior | $186,157 | ACAD 309000 1C – TITLE III |
| 2024-12-04 | Department of the Interior | $170,652 | ACAD 309000 – TITLE III AE SERVICES |
| 2021-09-20 | Department of the Interior | $118,688 | ARCHITECT AND ENGINEERING SERVICES, GREAT MEADOW DRAINAGE, ACADIA NATIONAL PARK, |
| 2022-06-02 | Department of the Interior | $109,966 | TITLE II ARCHITECT AND ENGINEERING SERVICES, REPLACE THE SCHOODIC WASTEWATER TRE |
| 2023-04-28 | Department of the Interior | $105,460 | ACAD AE SERVICES REPLACE CULVERT GREAT MEADOW TII |
| 2022-05-25 | Department of the Interior | $89,115 | TITLE II ARCHITECT AND ENGINEERING SERVICES TO REHABILITATE THE PARK LOOP ROAD S |
| 2021-09-20 | Department of the Interior | $85,730 | ARCHITECT AND ENGINEERING SERVICES TO REPLACE THE CULVERT ON PARK LOOP ROAD AT G |
| 2025-05-02 | Department of the Interior | $84,044 | ACAD – AE SERVICES DEMOLISH AND REPLACE SCHOODIC WASTEWATER TREATMENT FACILITY – |
| 2025-09-24 | Department of the Interior | $73,107 | ACAD 255256, REPLACE HARDEN FARM SEWAGE SYSTEM WITH CONNECTION TO MUNICIPAL FACI |
| 2023-05-15 | Department of the Interior | $67,404 | ACAD- REPLACE HARDEN FARM SEWER TI & TII |
| 2024-05-15 | Department of the Interior | $65,095 | ACAD -WINTER STORM RECOVERY A&E SUPPORT |
| 2019-08-08 | Department of the Interior | $60,614 | ACAD-T II REHAB BLACKWOODS AMPHITHEATER |
| 2019-08-07 | Department of the Interior | $58,035 | ACAD-T II SEAWALL AMPHITHEATER |
| 2022-05-12 | Department of the Interior | $52,807 | TITLE II ARCHITECT AND ENGINEERING SERVICES, CURATORIAL FIRE SUPPRESSION SYSTEM, |
| 2021-09-02 | Department of the Interior | $49,071 | ARCHITECT AND ENGINEERING OVERSIGHT SERVICES TO DEVELOP/UPDATE THE SPILL PREVENT |
| 2022-05-25 | Department of the Interior | $46,845 | TITLE II ARCHITECT AND ENGINEERING SERVICES, REHABILITATE SEAWALL CAMPGROUND MAI |
| 2021-04-01 | Department of the Interior | $40,303 | TITLE I ARCHITECT AND ENGINEERING SERVICES, REPLACE AND UPGRADE HEATING AND POWE |