LESKCA INCORPORATED Federal Contracts — Government Award History

Total (All Time)$9M
Latest FY$734,936
Primary AgencyDepartment of Energy

LESKCA INCORPORATED has received $9M in total federal contract awards
across 6 fiscal year(s). ▼ 15.3% vs FY2025 Peak year was FY2023 ($3M).
Primary awarding agency: Department of Energy.

Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).

Awards by Fiscal Year

Year Spending Total Contracts Top Agency
FY2026

$734,936 3건 Department of Energy
FY2025

$867,395 3건 Department of Energy
FY2024

$1.0M 5건 Department of Energy
FY2023

$2.9M 6건 Department of Energy
FY2022

$2.4M 11건 Department of Energy
FY2021

$1.2M 5건 Department of Energy

Notable Contracts

Date Agency Amount Description
2023-09-18 Department of Energy $1.6M EDGELY – FORMAN 69-KV TRANSMISSION LINE REROUTE, PENINSULA PADS AT STRS. 35/1, 3
2019-08-22 Department of Energy $1.6M FENCE, DRAINAGE, AND EROSION REPAIRS VARIOUS LOCATIONS UPPER GREAT PLAINS REGION
2022-09-01 Department of Energy $778,865 STEEL POLE FOUNDATIONS, BISMARCK – JAMESTOWN NO. 2, 230-KV TRANSMISSION LINE, S
2019-04-23 Department of Energy $733,846 CONSTRUCT MOUNT VERNON SUBSTATION, STAGE 05, SOUTH DAKOTA
2025-02-03 Department of Energy $653,213 FORT RANDALL – SIOUX CITY NO. 2 230-KV TRANSMISSION LINE, STRUCTURE 103/4, BANK
2024-09-09 Department of Energy $529,734 RIPRAP PROTECTION BISMARCK – JAMESTOWN NO. 1 230-KV TRANSMISSION LINE, STR. 77/1
2022-08-15 Department of Energy $519,690 BUILDING REPAIRS AND ROOFING, VARIOUS LOCATIONS, IA, SD
2023-03-17 Department of Energy $518,220 STEEL POLE FOUNDATIONS, FORT RANDALL – O.NEILL 115-KV TRANSMISSION LINE, STRS. 1
2022-08-05 Department of Energy $438,333 FARGO SUBSTATION, SERVICE AND SVS ADDITION BUILDING REPAIRS, SVS BUILDING ADDITI
2021-09-10 Department of Energy $371,093 FORT RANDALL TO SIOUX CITY 230KV TRANSMISSION LINE, STRUCTURE 103/4, ACCESS RAMP
2021-09-06 Department of the Interior $340,684 X:NOGRN, REPLACE VAULT TOILETS AT BADLANDS NATIONAL PARK
2023-04-17 Department of Energy $277,738 GRANDE PRAIRE – GRAND ISLAND 345-KV TRANSMISSION LINE STRUCTURE 216/3 – BANK STA
2023-08-22 Department of Energy $270,828 CHEYENNE COOLING AND BUILDING REPAIR
2026-02-12 Department of Energy $268,045 SPALDING, ELKTON, HERMOSA, HOPEWELL, ORCHARD COMMUNICATION SITE STANDARD CHAIN L
2021-08-23 Department of Energy $249,227 STEEL POLE FOUNDATIONS, FORMAN – SUMMIT 115-KV TRANSMISSION LINE, STRS. 121/5, 1
2026-03-09 Department of Energy $245,025 EDGELEY AND FORMAN SUBSTATIONS, SERVICE BUILDING ROOF REPLACEMENTS, NORTH DAKOTA
2026-02-25 Department of Energy $221,866 RAPID CITY SERVICE CENTER – GARAGE AND WAREHOUSE, ROOF AND INSULATON REPLACEMENT
2024-09-05 Department of Energy $172,134 FARGO SUBSTATION, SERVICE BUILDING ROOF REPLACEMENT
2021-01-27 Department of Energy $160,791 GRANDE PRAIRIE – GRAND ISLAND 345KV TRANSMISSION LINE, STRUCTURES 124/3 & 129/3,
2025-09-17 Department of Energy $159,793 GRAND ISLAND SUBSTATION, 345-KV CIRCUIT BREAKER FOUNDATION REMOVALS AND REPLACEM