SERES-ARCADIS SB JV, LLC Federal Contracts — Government Award History
Total (All Time)$30M
Latest FY$3M
Primary AgencyDepartment of Defense
SERES-ARCADIS SB JV, LLC has received $30M in total federal contract awards
across 5 fiscal year(s). ▼ 37.6% vs FY2022 Peak year was FY2020 ($18M).
Primary awarding agency: Department of Defense.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2024 | $2.9M | 3건 | Department of Defense | |
| FY2022 | $4.6M | 6건 | Department of Defense | |
| FY2021 | $3.0M | 3건 | Department of Defense | |
| FY2020 | $17.8M | 10건 | Department of Defense | |
| FY2019 | $2.2M | 4건 | Department of Defense |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2020-09-30 | Department of Defense | $5.1M | MID-ATLANTIC OPTIMIZED REMEDIATION CONTRACT |
| 2020-05-29 | Department of Defense | $3.7M | JOINT BASE ANDREWS OPTIMIZED REMEDIATION CONTRACT, JOINT BASE ANDREWS, MARYLAND |
| 2022-09-29 | Department of Defense | $3.4M | PHASE I RI AT PITTSBURGH AIR RESERVE STATION AND PITTSBURGH AIR NATIONAL GUARD B |
| 2020-09-28 | Department of Defense | $2.4M | NORTHEAST OPTIMIZED REMEDIATION CONTRACT |
| 2025-08-17 | Department of Defense | $2.1M | FT DRUM OASIS, NY AND TO INCORPORATE SECTION 889(A)(1)(B) ALSO KNOWN AS THE JOHN |
| 2020-09-25 | Department of Defense | $2.1M | CAMP CROFT THIRD PARTY SEEDING |
| 2021-03-26 | Department of Defense | $1.6M | DECISION DOCUMENTS/REMEDIAL ACTION/ LONG TERM MONITORING (LTM)/ MISC. SERVICES A |
| 2020-09-24 | Department of Defense | $1.4M | PROJECT MANAGEMENT SUPPORT AND PLANNING |
| 2024-07-09 | Department of Defense | $1.4M | TIME CRITICAL REMOVAL ACTION (TCRA) FOR PER- AND POLYFLUOROALKYL SUBSTANCES (PFA |
| 2020-09-30 | Department of Defense | $1.2M | FORT DETRICK, MD AND FOREST GLEN ANNEX, MD-ENVIRONMENTAL SERVICES |
| 2021-09-20 | Department of Defense | $1.2M | VARIOUS NATURAL RESOURCES SURVEYS IN SUPPORT OF INTEGRATED NATURAL RESOURCES MAN |
| 2024-09-30 | Department of Defense | $1.1M | SURVEY SUPPORT INRMP |
| 2019-12-17 | Department of Defense | $1.1M | EXCAVATION OF PCB CONTAMINATED SOIL LOCATED AT WALTER REED ARMY MEDICAL CENTER I |
| 2019-09-30 | Department of Defense | $977,377 | CONTRACTOR SHALL PREPARE FTGL-02 BALLFIELD LANDFILL COVER REMEDIAL DESIGN AT FOR |
| 2019-08-20 | Department of Defense | $753,897 | CONDUCT AN EXPANDED SITE INVESTIGATION (SI) AE SERVICES FOR NUMEROUS SITES AT FO |
| 2024-05-17 | Department of Defense | $407,342 | AOC-3 RELOCATION OF INJECTION WELL-2 |
| 2019-12-09 | Department of Defense | $313,711 | LUST REASSESSMENT (LUST CASE – 219009) AT BUILDING 15, FORMER WALTER REED ARMY M |
| 2020-07-24 | Department of Defense | $305,124 | NEW TASK ORDER CAMP VAN DORN |
| 2022-03-04 | Department of Defense | $296,603 | NEW TASK ORDER FOR FT. PICKENS |
| 2022-03-08 | Department of Defense | $284,835 | NEW TASK ORDER FOR BENEDICT FIELD |