SIA-STANTEC LLC Federal Contracts — Government Award History
Total (All Time)$5M
Latest FY$1M
Primary AgencyDepartment of Energy
SIA-STANTEC LLC has received $5M in total federal contract awards
across 4 fiscal year(s). ▲ 26.4% vs FY2023 Peak year was FY2024 ($1M).
Primary awarding agency: Department of Energy.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2024 | $1.5M | 6건 | Department of Energy | |
| FY2023 | $1.2M | 4건 | Department of Energy | |
| FY2022 | $1.1M | 5건 | Department of Energy | |
| FY2020 | $785,764 | 3건 | Department of Energy |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2019-09-26 | Department of Defense | $1.2M | LONG-TERM MONITORING |
| 2022-05-04 | Department of Energy | $594,929 | PROJECT: NETL VARP (VULNERABILITY ASSESSMENT & RESILIENCE PLAN) POC: GREGG SAWL |
| 2024-03-25 | Department of Energy | $583,944 | HYBRID WORKSPACE UPGRADES |
| 2023-04-03 | Department of Energy | $555,158 | EISA ENERGY AND WATER AUDITS FOR MGN AND PGH (FY23) |
| 2023-04-01 | Department of Energy | $512,927 | NETL ARC-FLASH HAZARD ANALYSIS & SHORT CIRCUIT STUDY (FY23) |
| 2024-09-01 | Department of Energy | $399,910 | ENGINEERING ELECTRICAL INFRASTRUCTURE AND FEASIBILITY STUDY AT DOE/NETL PITTSBUR |
| 2020-09-23 | Department of Energy | $362,081 | DESIGN – B-922 RECEPTION AREA/CONFERENCE ROOM RENOVATION |
| 2020-03-12 | Department of Energy | $335,327 | NETL PGH DESIGNS FOR 920 LOAD INTERRUPTER SWITCH REPLACEMENT DESIGN SWITCHGEAR |
| 2022-05-31 | Department of Energy | $284,770 | DIRECT AIR CAPTURE CENTER SITING STUDY AND 15% DESIGN |
| 2024-12-11 | Department of Energy | $262,860 | NETL PITTSBURGH, PA ACCELERATED BRINE LITHIUM EXTRACTION (ABLE) LABORATORY R&D D |
| 2024-03-13 | Department of Energy | $180,843 | NETL MORGANTOWN, WV TS-4 & TS-9 RESILIENCE AND SAFETY UPGRADES DESIGN |
| 2024-07-01 | Department of Energy | $145,963 | NETL MORGANTOWN B3, B17, AND B19 HVAC PROJECT DESIGNS |
| 2024-09-13 | Department of Energy | $142,683 | PITTSBURGH B83 ROOF AND AC PLATFORM REPLACEMENT |
| 2021-05-25 | Department of Energy | $115,598 | ENERGY AND WATER AUDIT EVALUATION SERVICES AT NETL-ALBANY, OR SITE |
| 2020-09-21 | Department of Energy | $88,356 | DESIGN – B-922 CHILLER REPLACEMENT NETL PITTSBURGH, PA |
| 2022-05-23 | Department of Energy | $73,789 | MORGANTOWN SITE RETENTION POND DRAINAGE PIPE REPAIR |
| 2022-07-05 | Department of Energy | $60,814 | BUILDING 901 ROOF REPLACEMENT |
| 2023-07-01 | Department of Energy | $55,985 | NETL PGH MOTOR CONTROL CENTER (B84 MCC04) EVALUATION AND DESIGN IN PITTSBURGH, P |
| 2022-05-20 | Department of Energy | $53,988 | NETL PITTSBURGH B-167 ROOF REPLACEMENT DESIGN |
| 2022-11-01 | Department of Energy | $47,099 | NETL – ELECTRIC VEHICLE CHARGING STATIONS EVALUATION AND DESIGN IN MORGANTOWN, W |