SJV2 Federal Contracts — Government Award History
Total (All Time)$43M
Latest FY$6M
Primary AgencyDepartment of Defense
SJV2 has received $43M in total federal contract awards
across 6 fiscal year(s). ▲ 36.6% vs FY2024 Peak year was FY2022 ($13M).
Primary awarding agency: Department of Defense.
Data covers largest contracts by award amount. Source: USASpending.gov (FPDS).
Awards by Fiscal Year
| Year | Spending | Total | Contracts | Top Agency |
|---|---|---|---|---|
| FY2025 | $5.8M | 4건 | Department of Defense | |
| FY2024 | $4.2M | 13건 | Department of Defense | |
| FY2023 | $5.5M | 19건 | Department of Defense | |
| FY2022 | $12.6M | 17건 | Department of Defense | |
| FY2021 | $11.8M | 34건 | Department of Defense | |
| FY2020 | $2.9M | 13건 | Department of Defense |
Notable Contracts
| Date | Agency | Amount | Description |
|---|---|---|---|
| 2022-07-29 | Department of Defense | $4.9M | THIS REQUIREMENT REPLACES THE ROOF AT BUILDING 705. |
| 2024-10-28 | Department of Defense | $3.7M | REPLACE JBAB BASEWIDE TRANSFORMERS AND SWITCHGEARS |
| 2022-09-26 | Department of Defense | $1.5M | DEMOLISH OLD FIRESTONE, B1568 |
| 2021-07-15 | Department of Defense | $1.4M | REPAIR ROOF 4TH WING BANCROFT |
| 2023-07-31 | Department of Defense | $1.4M | REPAIR SEWAGE LIFT STATIONS |
| 2025-09-30 | Department of Defense | $1.3M | THIS PROJECT SHALL CONSIST OF REPLACING THE LEAKING 1000KVA TRANSFORMER T3320, I |
| 2022-07-29 | Department of Defense | $1.2M | THIS REQUIREMENT REPAIRS THE DAMAGED FOUNDATION AT BUILDING 2016 AND REPLACES TH |
| 2021-04-16 | Department of Defense | $1.2M | REPAIR ROOF SYSTEMS FOR 7TH AND 8TH WINGS, BANCROFT HALL |
| 2020-09-17 | Department of Defense | $1.0M | REPLACE LIME SLUDGE TANK |
| 2024-05-17 | Department of Defense | $943,302 | REPLACE HEATING VENTILATION AND AIR CONDITIONING EQUIPMENT AT THE FITNESS CENTER |
| 2021-09-15 | Department of Defense | $941,365 | BUILDING 153 SUITE RENOVATION |
| 2021-08-27 | Department of Defense | $789,968 | X005 REPAIR ROOF, 6TH WING BANCROFT HALL, USNA-1016 |
| 2022-03-29 | Department of Defense | $788,931 | REPAIR ROOF – USNA-258 |
| 2021-07-16 | Department of Defense | $785,177 | ROOF REPAIR WING 5 BANCROFT |
| 2021-08-26 | Department of Defense | $770,889 | REPAIR HALSEY FIELD HOUSE FLAT ROOF – MULTIPLE LEAKS, BLDG. |
| 2022-03-23 | Department of Defense | $761,953 | REPLACE HANGAR APRON TRENCH DRAIN AT BUILDING 1117 |
| 2022-09-01 | Department of Defense | $720,589 | REPAIR BULLET TRAP DESIGN ONLY. |
| 2023-09-29 | Department of Defense | $708,395 | REPLACE HEATING VENTILATION AIR CONDITIONING AND DOORS AT BUILDING 711. |
| 2024-08-05 | Department of Defense | $616,549 | RV STORAGE LOT |
| 2021-05-12 | Department of Defense | $611,182 | REPAIR WATER LATERALS IN RIDGEVIEW, PHASE 2 |